PROJECT SCHEDULE:

The North Richmond Specific Plan will be prepared over the next 12 months.
 

Winter 2008

Project Initiation, Kick-off Meeting and Site Tour

Winter - Spring 2008

Community Assessment Interviews and Outreach

Winter – Spring 2008

Background Data Research

Opportunities & Constraints Analysis

Fall 2008 – Winter 2009

Prepare Plan Vision and Land Use Alternatives

February 7, 2009

Public Workshop: Plan Vision and Land Use Alternatives

Spring - Summer 2009

Review Plan Vision and Land Use Alternatives and Identify Preferred Land Use Concept

Public Workshop (date to be determined): Input and Selection of Preferred Land Use Concept

Board of Supervisors Study Session (date to be determined): Input and Selection of Preferred Land Use Concept

Summer 2009

Initiate Environmental Impact Report (EIR) based on Preferred Land Use Concept

Conduct Scoping Meeting for EIR

Prepare Specific Plan (Public Review - Draft) and Draft EIR

Fall  2009

Release Specific Plan (Public Review - Draft) and Draft EIR for public review and comment

Winter - Spring 2010

Prepare Specific Plan (Hearing Draft) and Response to Comments/Final EIR

 

 

April 19, 2010
3pm

Scoping Session for the EIR at Ted Wotten Building , West County Wastewater District Treatment Plant, 2377 Garden Tract Road , Richmond

 

Note: Additional community meetings and/or public workshops than those listed above may be scheduled, as necessary.

 